Pipeline Name | Pipeline Short Name | Classification | Nameplate Rating (TJ) |
---|---|---|---|
Port Campbell to Adelaide | PCA | Transmission | 251 |
Port Campbell to Iona | PCI | Transmission | 400 |
Mortlake | MORT | Transmission | 150 |
Effective 01/07/2024
Updated 25/06/2024
Pipeline Name | Pipeline Short Name | Classification | Nameplate Rating (TJ) |
---|---|---|---|
Port Campbell to Adelaide | PCA | Transmission | 251 |
Port Campbell to Iona | PCI | Transmission | 400 |
Mortlake | MORT | Transmission | 150 |
Effective 01/07/2024
Updated 25/06/2024
Pipeline | Name | Location | Direction | Type | Connects to | Gas Type |
---|---|---|---|---|---|---|
PCA | Athena (PCA) | Port Campbell | Receipt | Production Facility | Athena Gas Plant (formerly Minerva Gas Plant) | Natural Gas |
Otway (PCA) | Iona | Receipt | Production Facility | Otway Gas Plant | ||
UGS | Iona | Receipt/Delivery | Storage Facility | Iona Gas Plant | ||
Langley (PCA) | Port Campbell | Receipt/Delivery | Pipeline Interconnection | PCI Pipeline | N/A | |
Poolaijelo | Poolaijelo | Delivery | Pipeline Interconnection | SESA Pipeline | ||
Naracoorte | Naracoorte | Delivery | Industrial | Teys Australia | ||
Jervois | Jervois | Delivery | Industrial | Beston Pure Dairies | ||
Bolivar | Adelaide | Delivery | Industrial | SA Water | ||
Cavan | Adelaide | Delivery | Network Interconnection (STTM) | Adelaide Distribution Network | ||
Torrens Island | Adelaide | Delivery | GPG | Torrens Island Power Station | ||
Quarantine | Adelaide | Delivery | GPG | Quarantine Power Station | ||
Pelican Point | Adelaide | Delivery | GPG and Pipeline Interconnection | Pelican Point Power Station and MAPS | ||
PCI | Athena (PCI) | Port Campbell | Receipt/Delivery | Production Facility | Athena Gas Plant (formerly Minerva Gas Plant) | Natural Gas |
Otway (PCI) | Iona | Receipt | Production Facility | Otway Gas Plant | ||
M-UGS | Iona | Receipt/Delivery | Storage Facility | Iona Gas Plant | ||
Langley (PCI) | Port Campbell | Receipt/Delivery | Pipeline Interconnection | PCA Pipeline | N/A | |
Mortlake | Iona | Receipt/Delivery | Pipeline Interconnection | Mortlake Pipeline | ||
SWP | Iona | Receipt/Delivery | Pipeline Interconnection (DWGM) | South West Pipeline | ||
Otway UFM 4 | Iona | Receipt/Delivery | Pipeline Interconnection (DWGM) | South West Pipeline | ||
MPSWCP | Iona | Delivery | Pipeline Interconnection (DWGM) | South West Pipeline | ||
MORT | MIJ-001 | Iona | Receipt/Delivery | Pipeline Interconnection | PCI Pipeline | N/A |
Mortlake PRMS | Mortlake | Delivery | GPG | Mortlake Power Station |
Pipeline | PCA |
---|---|
Design Life, Pipeline: | 80 years |
Design Life, Cathodic Protection System: | 40 years |
Commissioning Date: | January 2004 |
Maximum Allowable Operating Pressure: | 15,306 kPag |
Installed Length: | 689 km |
Pipeline | PCI |
---|---|
Design Life, Pipeline: | 80 years |
Design Life, Cathodic Protection System: | 40 years |
Commissioning Date: | January 2004 |
Maximum Allowable Operating Pressure: | 15,306 kPag |
Installed Length: | 12 km |
Pipeline | Mortlake |
---|---|
Design Life, Pipeline: | 25 years |
Design Life, Cathodic Protection System: | 20 years |
Commissioning Date: | February 2011 |
Maximum Allowable Operating Pressure: | 15,306 kPag |
Installed Length: | 82 km |